The Rules mandate that mining should be done as per the approved mining plan, scheme of mining and final quarry closure plans. Provision have been given in KOMPAS portal to upload mining plan and other documents. Since mining has to be done as per approved mining plans, improper entry of mining plans in KOMPAS may lead to undesired actions by the lessee which can not be reverted.
Since, Geologists are under various scanners, any error detected in future may make Geologists answerable. So utmost care should be taken to approve mining plan and related documents and to enter the mining plan data into KOMPAS.2.
Types of mining plan documents
In KMMC Rules, three types
of documents are mentioned, namely
1. Mining
Plan with progressive mine closure plan
2. Scheme
of Mining
3. Final
quarry closure plan
The lessee can request geologist
for submission of modified documents and if geologist find that the request is
genuine, then the modified documents can be approved. Similarly, Geologist can
instruct lessee to modify mining plan document.
So, following additional
documents are also submitted, namely
1. Modified
mining plan with progressive mine closure plan (Rule 56)
2. Modified
scheme of mining (from Rule 68, it can be seen that modification of scheme is
permitted)
3. Modified
quarry closure plan (Rule 60)
3.
Entry of data of different types of
mining plan documents
1.
Mining Plan with progressive mine
closure plan
Mining plan with progressive
mine closure plans are prepared for the entire period of lease. If the area is
very large, in the mining plan submitted, RQP shall find out the total resource
and mention that the life of the mining. Large area mines may have resource for
mining up to 30 or more years. RQP can mention that during the lease period the
lessee would mine a specific quantity and balance quantity will be mined by
renewing the lease.
So, the period of mining
plan with progressive mine closure plan is the period of lease (Rule 67(1)).
However, KMMC Rules clearly mentions that the lessee has to give separately the
scheme for first five years specifying the area he proposes to excavate (Rule
55). It is also mentioned that the lessee has to give tentative scheme for the
next five years also (Rule 55). So in a mining plan submitted for 12 year
lease, there shall be following details:
1. Scheme
of mining for first five years
2. Tentative
scheme of mining for next five years.
It is noticed that in mining
plans, the RQP gives production plan for 12 years. There is no harm in giving
the scheme for 12 years, but the first five year scheme is what a geologist should
be bothered about.
In KMMC Rules, it is not
mentioned what all details should be there in a modified mining plan. However,
from the information gathered from IBM and as per the existing KMMC Rules, it
can be concluded as follows:
·
A modified mining plan is submitted as per
the instruction of the geologist. For example, the lessee has made gross
violation of the mining plan (for example –excess production than the approved
scheme) and geologist is not in a position to allow mining for the balance
scheme period.
·
A modified mining plan is submitted when
there is a major error in the approved mining plan (for example, mineable
reserve shown in mining plan exceeds what is actually present in the mine).
This case does not arise if proper scrutiny of mining plan is done at the time
of approval of mining plan
·
In the modified mining plan also RQP has to
give the scheme of mining for first five years and tentative scheme of mining
for next five years. It may be noted that first five means, the first five year
period mentioned in the original mining plan.
Eg:
A mining plan was prepared for 12 years and mining started on April 1st
of 2015. So the first five year scheme is for the period:
2015-16
2016-17
2017-18
2018-19
2019-20
If
the geologist ask the lessee to modify the mining plan in August 2018 or the
lessee wanted to modify the mining plan in August 2008 then they can do so. In
the modified mining plan, reasons for modification, mining already done etc.
should be mentioned. In the modified mining plan, scheme of mining should be
limited to original scheme of mining.
2015-16
– Proposed production- 50000 Production as per KOMPAS - 40000
2016-17-
Proposed production- 50000. Production as per KOMPAS – 49000
2017-18
– Proposed production- 50000.Production as per KOMPAS – 45000
2018-19
– Proposed production -50000. Production as per KOMPAS -20000 – Modified
production proposed – 80000
2019-20
– Proposed production -50000 Modified production proposed -80000
Year |
Mining
Plan (Document 1) |
Modified
Mining plan (Document 2) |
Actual
production |
Remarks |
2015-16 |
50000 |
|
40000 |
|
2016-17 |
50000 |
|
49000 |
|
2017-18 |
50000 |
|
45000 |
|
2018-19 |
50000 |
80000 |
20000 |
|
2018-20 |
50000 |
80000 |
|
|
It
is very important to note that each plan document has to be entered separately
which means, if a modified mining plan is submitted, then in KOMPAS, the
modified mining plan is to be entered separately. After entry you can see
previous documents and at the bottom of the mining plan entry screen, you can
see based details of actual approved scheme. In the above case, in view mining
plan you can see the following:
Year |
Document |
Proposed
production |
Actual
production |
Remarks |
2015-16 |
1 |
50000 |
40000 |
|
2016-17 |
1 |
50000 |
49000 |
|
2017-18 |
1 |
50000 |
45000 |
|
2018-19 |
2 |
80000 |
20000 |
View
of mining plan after entry of modified mining plan in August 2018 |
2019-20 |
2 |
80000 |
|
|
Note:
It is observed that due to some programming issues, at present the document no
2 is appearing as document 1. This correction has been intimated earlier.
Editing
of approved data |
When
a modified mining plan is submitted, instead of entering it as new
document, existing mining plan is
modified by deleting the old data |
Result |
There
is no record of previous scheme of mining and actual mining carried out.
Mismatch in data. It will appear as if mining started only on a later period of
time. Old approved mining plan document disappears. |
Example: Scenario
mentioned above |
View
mining plan scheme will appear as follows: 2018-19 - Proposed 80000 – Actual 20000 2019-20
– Proposed 80000- Acutal 0 2020-21-
Proposed 40000 – Actual 0 2021-22
– Proposed 50000- Actual 0 2021-2023-
Proposed 30000-Actual 0 |
What
mistake was made |
The
person entered the data edited original mining plan and entered scheme of
mining for next five years (sometimes even more) and old plan details and
scheme and actual production missing in mining plan |
What
KOMPAS do |
KOMPAS
permits mining till 2023 March |
Legal
issue |
The
geologist is permitting the lessee to mine mineral without submission of
statutory document “Scheme of mining” which could be interpreted as dereliction
of duty. |
Resolution |
Since
there is no possibility of time travel, there is nothing a geologist can do
about the past actions. Geologist can seek the help of NIC. However, all data
entry of mining plan in KOMPAS can be reviewed with the help of PMU staff to
make sure that the data entry is proper. |
3. Scheme of Mining
2.
What was actually done during previous five
years
3.
What is proposed for next five years (or 2
years in case of 2nd scheme of mining)
So
when a scheme of mining is submitted, it is entered as a new document (in the
example cited above, it is document number 3. After entry of scheme of mining,
in this case, there will be two previous documents namely- mining plan and modified
mining plan.
After
entry of scheme of mining, in the view mining plan window following scheme will
appear:
Year |
Document |
Proposed
production |
Actual
production |
Remarks |
2015-16 |
1 |
50000 |
40000 |
|
2016-17 |
1 |
50000 |
49000 |
|
2017-18 |
1 |
50000 |
45000 |
|
2018-19 |
2 |
80000 |
55000 |
|
2019-20 |
2 |
80000 |
78000 |
|
2020-21 |
3 |
60000 |
|
Viewed after Scheme of entry in April 2020 |
2021-22 |
3 |
60000 |
|
|
2022-23 |
3 |
40000 |
|
|
2023-24 |
3 |
40000 |
|
|
2024-25 |
3 |
50000 |
|
|
It
is very rare to have this scenario (this sort of scenario arises only when the
mine was not visited for the entire period of mining and all of a sudden
geologist want to modify the scheme as only little balance is left for mining).
Suppose a modified scheme is submitted in May 2023. Then in this scheme of
mining, the production proposal till 2024 is to be submitted and entered. After
the entry, following will be the view mining plan window:
Year |
Document |
Proposed
production |
Actual
production |
Remarks |
2015-16 |
1 |
50000 |
40000 |
|
2016-17 |
1 |
50000 |
49000 |
|
2017-18 |
1 |
50000 |
45000 |
|
2018-19 |
2 |
80000 |
55000 |
|
2019-20 |
2 |
80000 |
78000 |
|
2020-21 |
3 |
60000 |
55000 |
|
2021-22 |
3 |
60000 |
45000 |
|
2022-23 |
3 |
40000 |
35000 |
|
2023-24 |
4 |
10000 |
4000 |
Compounded
for illegal mining (80000) |
2024-25 |
4 |
10000 |
|
|
5. The
final quarry closure plan
There
is a provision to enter the final quarry closure plan. It is entered as final
document and in case, the quantity of final year is different (on account of
excess mining), the same can be entered and the document will appear as
document number 5.
6. On
expiry of lease
On
expiry of lease, if one check the view mining plan window, he will be able to
see full details of scheme of mining in one screen and each document can be
viewed separately (text, annexure and map)
7.
4.
![]() |
Mining Plan data entry screen and important buttons/links |
Disclaimer:
The
author assumes no responsibility or liability for any errors or omissions in
the content of this report. The information contained in this report is provided
on an "as is" basis with no guarantees of completeness, accuracy,
usefulness or timeliness.
0 Comments