About Mining Plan Suite 2.0

By: Biju Sebastian

Mining Plan Suite 2.0 is a set of four applications developed to assist in the preparation, analysis and verification of quarry mining plans and mining operations using digital terrain data, boundary information and 3D surface analysis.

The Suite brings together four related applications:

  1. Mining Plan
  2. Scheme of Mining
  3. Volume & Compliance
  4. 3D Mine Viewer

Each application has a specific purpose, but the four applications are designed to work together as part of a common mining-analysis workflow.

The Suite is intended primarily for geologists, mining engineers, mining plan preparers and officials involved in the scrutiny or verification of quarry operations.

The applications use GIS-based terrain and surface analysis. The accuracy of the results depends on the quality, resolution and positional accuracy of the input data. The results should therefore be considered in conjunction with appropriate field survey data where precise measurements are required.


1. Mining Plan



Purpose

The Mining Plan application is used to create a digital representation of the proposed quarry development based on the existing terrain.

It helps the user to:

  • Load the quarry/lease boundary.
  • Create the pre-mining terrain surface.
  • Examine topographic contours.
  • Design quarry benches.
  • Apply the required mining and safety buffers.
  • Estimate the mineable mineral reserve based on the proposed quarry geometry.
  • Visualise the proposed excavation in 3D.

The application provides a digital basis for examining the proposed mining geometry before actual extraction.

Main functions

Load pre-mining surface
Loads the existing ground surface from the available elevation data.

Topographic contours
Generates and displays contours from the terrain surface to understand the existing topography.

Bench design and cutting
Allows the proposed quarry benches to be designed and the excavation to be modelled.

Bench-wise mineable reserve
Calculates the volume of the mineable material associated with the designed quarry benches.

Main inputs required

  • Quarry / lease boundary KML or KMZ
  • Pre-mining elevation data
    • SRTM elevation data, or
    • LiDAR/other high-resolution terrain data where available
  • Mining parameters, such as:
    • Bench height
    • Bench width/offset
    • Required buffer/preserved strip
    • Mineral specific gravity
    • Overburden specific gravity, where applicable
    • Soil thickness, where applicable

Output

The application produces a proposed bench model and corresponding volume/reserve information, including bench-wise mineable reserve.


2. Scheme of Mining

Purpose

The Scheme of Mining application is intended to examine the mining carried out during a particular scheme period and to model the proposed extraction for the next stage of quarry development.

The application compares the terrain before and after mining and helps determine the quantity extracted during the scheme period and the remaining mineable reserve.

The present Suite is designed around a 5-year scheme period.

Main functions

Pre/Post-mining DTM
Compares the terrain surface before mining with the surface after mining.

Volume extracted in period
Determines the volume represented by the difference between the pre-mining and post-mining surfaces.

Reserve for next period
Uses the remaining mineralised/mineable volume to examine the reserve available for the subsequent period.

Topographic contours
Displays contours of the relevant surface for understanding the terrain and proposed mining geometry.

Main inputs required

  • Quarry / lease boundary
  • Pre-mining surface
  • Post-mining survey surface, preferably from:
    • Drone LiDAR, or
    • Other suitable high-resolution survey data
  • Mining Plan / proposed mine geometry, where required for modelling the subsequent period
  • Mining parameters, such as:
    • Bench height
    • Bench width/offset
    • Mineral specific gravity
    • Overburden/soil parameters, where applicable

Basic workflow

Pre-mining surface → Post-mining surface → Calculate extraction → Determine remaining reserve → Model next scheme period

This makes the application useful for analysing the progress of mining from one scheme period to the next.


3. Volume & Compliance

Purpose

The Volume & Compliance application is intended for checking the actual mining carried out against the permitted/planned mining geometry.

It compares the pre-mining and post-mining surfaces and identifies the volume of material removed or deposited.

It also examines whether mining has occurred within the permitted mining area and highlights areas requiring attention.

Main functions

Pre/Post-mining surfaces
Loads and compares the original and present terrain surfaces.

Volume between surfaces
Calculates the difference between the two surfaces.

The results can include:

  • Ore volume
  • Ore tonnage
  • Excavation volume
  • Filling/deposition volume

Theoretical benches
Creates the theoretical bench model based on the original mining geometry/parameters.

Plan vs actual deviation
Compares the actual post-mining terrain with the planned mining geometry.

This can help identify conditions such as:

  • Excess mining
  • Mining outside the lease/boundary
  • Mining within a no-mining/buffer zone
  • Filling or deposition
  • Deviation from the proposed bench configuration

Main inputs required

  • Quarry / lease boundary KML/KMZ
  • Pre-mining surface
  • Post-mining surface
  • Approved/proposed mining geometry, where applicable
  • Mining parameters such as:
    • Bench height
    • Bench offset/width
    • Mineral specific gravity
    • Overburden specific gravity
    • Soil thickness
    • Applicable buffer/preserved strip

Output

The application provides a quantitative comparison of the two surfaces and identifies areas where the actual excavation differs from the planned mining configuration.

The results should be used as a GIS-based technical assessment and, where required, verified against field survey data.


4. 3D Mine Viewer



Purpose

The 3D Mine Viewer provides a three-dimensional visual representation of the quarry and its surrounding terrain.

It is primarily a visualisation and examination tool rather than a reserve-calculation application.

The 3D environment helps the user understand:

  • Quarry depth
  • Bench configuration
  • Terrain form
  • Elevation differences
  • Slopes
  • Boundary location
  • Relationship between the quarry and surrounding terrain

Main functions

Orthophoto draped on terrain
Displays aerial/satellite imagery over the terrain surface.

Rotate, pan and zoom
Allows the user to examine the quarry from different viewing directions and scales.

Distance, elevation and slope
Provides tools for examining spatial and terrain characteristics.

Boundary on Google Map
Allows the quarry boundary to be viewed in its geographic context.

Main inputs required

Depending on the data available:

  • Quarry / lease boundary KML/KMZ
  • Elevation/terrain surface
  • LiDAR or other high-resolution terrain data, where available
  • Satellite/orthophoto imagery, where applicable

Output

The application produces an interactive 3D representation of the quarry and terrain, allowing the user to visually inspect the site and the modelled mine geometry.


How the Four Applications Work Together

The four applications are not independent tools. They can be used as a sequence.

1. Mining Plan

Existing terrain → Bench design → Proposed mineable reserve

↓

2. Scheme of Mining

Previous surface → Actual post-mining surface → Extraction during scheme period → Remaining reserve / next scheme

↓

3. Volume & Compliance

Original surface + Post-mining surface + Planned geometry → Actual excavation and compliance analysis

↓

4. 3D Mine Viewer

Terrain + mine geometry + imagery → Interactive 3D visualisation

This allows the user to move from planning, to scheme-based mining, to verification, and finally to 3D visual examination.


Data Requirements

The quality of the result depends mainly on the quality of the input data.

Boundary Data

The quarry/lease boundary should preferably be provided as a KML or KMZ file containing the correct boundary pillar coordinates.

Elevation Data

The Suite can work with terrain/elevation data appropriate to the particular application.

For general terrain analysis, SRTM-based elevation may be used. For detailed quarry analysis, drone LiDAR or other high-resolution survey data provides a much more detailed representation of the actual quarry surface.

Pre-mining Surface

The pre-mining surface represents the terrain before the mining operation or before the period being examined.

Post-mining Surface

The post-mining surface represents the actual terrain after mining during the period under examination.

For compliance and scheme analysis, the accuracy of the post-mining surface is particularly important.


Important Note on Accuracy

The applications perform digital terrain and GIS-based calculations. The accuracy of the results depends on:

  • Accuracy of the boundary coordinates
  • Resolution and accuracy of the elevation data
  • Quality of the LiDAR/DTM survey
  • Correct identification of the pre-mining and post-mining surfaces
  • Correct mining parameters entered by the user

The calculated areas, elevations and volumes should therefore not be treated as a substitute for an appropriate DGPS, Total Station, drone-LiDAR or other professional survey where legally or technically precise measurements are required.


Getting Started

From the Mining Plan Suite 2.0 home page, select the application appropriate to the task:

Mining Plan
For preparing and examining the proposed quarry bench design and mineable reserve.

Scheme of Mining
For analysing extraction during a scheme period and examining the reserve available for subsequent mining.

Volume & Compliance
For comparing actual excavation with the planned mining geometry and identifying deviations such as excess mining, outside mining and filling.

3D Mine Viewer
For interactive three-dimensional visualisation and examination of the quarry.