About Mining Plan Suite 2.0
By: Biju Sebastian
Mining Plan Suite 2.0 is a set of four applications
developed to assist in the preparation, analysis and verification of quarry
mining plans and mining operations using digital terrain data, boundary
information and 3D surface analysis.
The Suite brings together four related applications:
- Mining
Plan
- Scheme
of Mining
- Volume
& Compliance
- 3D
Mine Viewer
Each application has a specific purpose, but the four
applications are designed to work together as part of a common mining-analysis
workflow.
The Suite is intended primarily for geologists, mining
engineers, mining plan preparers and officials involved in the scrutiny or
verification of quarry operations.
The applications use GIS-based terrain and surface analysis.
The accuracy of the results depends on the quality, resolution and positional
accuracy of the input data. The results should therefore be considered in
conjunction with appropriate field survey data where precise measurements are
required.
1. Mining Plan
Purpose
The Mining Plan application is used to create a
digital representation of the proposed quarry development based on the existing
terrain.
It helps the user to:
- Load
the quarry/lease boundary.
- Create
the pre-mining terrain surface.
- Examine
topographic contours.
- Design
quarry benches.
- Apply
the required mining and safety buffers.
- Estimate
the mineable mineral reserve based on the proposed quarry geometry.
- Visualise
the proposed excavation in 3D.
The application provides a digital basis for examining the
proposed mining geometry before actual extraction.
Main functions
Load pre-mining surface
Loads the existing ground surface from the available elevation data.
Topographic contours
Generates and displays contours from the terrain surface to understand the
existing topography.
Bench design and cutting
Allows the proposed quarry benches to be designed and the excavation to be
modelled.
Bench-wise mineable reserve
Calculates the volume of the mineable material associated with the designed
quarry benches.
Main inputs required
- Quarry
/ lease boundary KML or KMZ
- Pre-mining
elevation data
- SRTM
elevation data, or
- LiDAR/other
high-resolution terrain data where available
- Mining
parameters, such as:
- Bench
height
- Bench
width/offset
- Required
buffer/preserved strip
- Mineral
specific gravity
- Overburden
specific gravity, where applicable
- Soil
thickness, where applicable
Output
The application produces a proposed bench model and
corresponding volume/reserve information, including bench-wise mineable
reserve.
2. Scheme of Mining
Purpose
The Scheme of Mining application is intended to
examine the mining carried out during a particular scheme period and to model
the proposed extraction for the next stage of quarry development.
The application compares the terrain before and after mining
and helps determine the quantity extracted during the scheme period and the
remaining mineable reserve.
The present Suite is designed around a 5-year scheme
period.
Main functions
Pre/Post-mining DTM
Compares the terrain surface before mining with the surface after mining.
Volume extracted in period
Determines the volume represented by the difference between the pre-mining and
post-mining surfaces.
Reserve for next period
Uses the remaining mineralised/mineable volume to examine the reserve available
for the subsequent period.
Topographic contours
Displays contours of the relevant surface for understanding the terrain and
proposed mining geometry.
Main inputs required
- Quarry
/ lease boundary
- Pre-mining
surface
- Post-mining
survey surface, preferably from:
- Drone
LiDAR, or
- Other
suitable high-resolution survey data
- Mining
Plan / proposed mine geometry, where required for modelling the
subsequent period
- Mining
parameters, such as:
- Bench
height
- Bench
width/offset
- Mineral
specific gravity
- Overburden/soil
parameters, where applicable
Basic workflow
Pre-mining surface → Post-mining surface → Calculate
extraction → Determine remaining reserve → Model next scheme period
This makes the application useful for analysing the progress
of mining from one scheme period to the next.
3. Volume & Compliance
Purpose
The Volume & Compliance application is intended
for checking the actual mining carried out against the permitted/planned mining
geometry.
It compares the pre-mining and post-mining surfaces
and identifies the volume of material removed or deposited.
It also examines whether mining has occurred within the
permitted mining area and highlights areas requiring attention.
Main functions
Pre/Post-mining surfaces
Loads and compares the original and present terrain surfaces.
Volume between surfaces
Calculates the difference between the two surfaces.
The results can include:
- Ore
volume
- Ore
tonnage
- Excavation
volume
- Filling/deposition
volume
Theoretical benches
Creates the theoretical bench model based on the original mining
geometry/parameters.
Plan vs actual deviation
Compares the actual post-mining terrain with the planned mining geometry.
This can help identify conditions such as:
- Excess
mining
- Mining
outside the lease/boundary
- Mining
within a no-mining/buffer zone
- Filling
or deposition
- Deviation
from the proposed bench configuration
Main inputs required
- Quarry
/ lease boundary KML/KMZ
- Pre-mining
surface
- Post-mining
surface
- Approved/proposed
mining geometry, where applicable
- Mining
parameters such as:
- Bench
height
- Bench
offset/width
- Mineral
specific gravity
- Overburden
specific gravity
- Soil
thickness
- Applicable
buffer/preserved strip
Output
The application provides a quantitative comparison of the
two surfaces and identifies areas where the actual excavation differs from the
planned mining configuration.
The results should be used as a GIS-based technical
assessment and, where required, verified against field survey data.
4. 3D Mine Viewer
Purpose
The 3D Mine Viewer provides a three-dimensional
visual representation of the quarry and its surrounding terrain.
It is primarily a visualisation and examination tool rather
than a reserve-calculation application.
The 3D environment helps the user understand:
- Quarry
depth
- Bench
configuration
- Terrain
form
- Elevation
differences
- Slopes
- Boundary
location
- Relationship
between the quarry and surrounding terrain
Main functions
Orthophoto draped on terrain
Displays aerial/satellite imagery over the terrain surface.
Rotate, pan and zoom
Allows the user to examine the quarry from different viewing directions and
scales.
Distance, elevation and slope
Provides tools for examining spatial and terrain characteristics.
Boundary on Google Map
Allows the quarry boundary to be viewed in its geographic context.
Main inputs required
Depending on the data available:
- Quarry
/ lease boundary KML/KMZ
- Elevation/terrain
surface
- LiDAR
or other high-resolution terrain data, where available
- Satellite/orthophoto
imagery, where applicable
Output
The application produces an interactive 3D representation
of the quarry and terrain, allowing the user to visually inspect the site
and the modelled mine geometry.
How the Four Applications Work Together
The four applications are not independent tools. They can be
used as a sequence.
1. Mining Plan
Existing terrain → Bench design → Proposed mineable
reserve
↓
2. Scheme of Mining
Previous surface → Actual post-mining surface →
Extraction during scheme period → Remaining reserve / next scheme
↓
3. Volume & Compliance
Original surface + Post-mining surface + Planned geometry
→ Actual excavation and compliance analysis
↓
4. 3D Mine Viewer
Terrain + mine geometry + imagery → Interactive 3D
visualisation
This allows the user to move from planning, to scheme-based
mining, to verification, and finally to 3D visual examination.
Data Requirements
The quality of the result depends mainly on the quality of
the input data.
Boundary Data
The quarry/lease boundary should preferably be provided as a
KML or KMZ file containing the correct boundary pillar coordinates.
Elevation Data
The Suite can work with terrain/elevation data appropriate
to the particular application.
For general terrain analysis, SRTM-based elevation may be
used. For detailed quarry analysis, drone LiDAR or other high-resolution
survey data provides a much more detailed representation of the actual
quarry surface.
Pre-mining Surface
The pre-mining surface represents the terrain before the
mining operation or before the period being examined.
Post-mining Surface
The post-mining surface represents the actual terrain after
mining during the period under examination.
For compliance and scheme analysis, the accuracy of the
post-mining surface is particularly important.
Important Note on Accuracy
The applications perform digital terrain and GIS-based
calculations. The accuracy of the results depends on:
- Accuracy
of the boundary coordinates
- Resolution
and accuracy of the elevation data
- Quality
of the LiDAR/DTM survey
- Correct
identification of the pre-mining and post-mining surfaces
- Correct
mining parameters entered by the user
The calculated areas, elevations and volumes should
therefore not be treated as a substitute for an appropriate DGPS, Total
Station, drone-LiDAR or other professional survey where legally or
technically precise measurements are required.
Getting Started
From the Mining Plan Suite 2.0 home page, select the
application appropriate to the task:
Mining Plan
For preparing and examining the proposed quarry bench design and mineable
reserve.
Scheme of Mining
For analysing extraction during a scheme period and examining the reserve
available for subsequent mining.
Volume & Compliance
For comparing actual excavation with the planned mining geometry and
identifying deviations such as excess mining, outside mining and filling.
3D Mine Viewer
For interactive three-dimensional visualisation and examination of the quarry.